CONTRACTOR PROJECT DATE SUBJECT
: BOQ
LOCATION ATTENTION
ITEM
DESCRIPTION/PARTICULAR
A.
PRELIMINARIES (General requirements)
a
ACCEPTANCE OF CONDITIONS Mobilization.Demobilization
1 b c 2 a b B. 1 a b a 2 a b c d e f g 3 a 4 a b
Project Management and supervision Temporary Facilities MISCELLANEOUS PROJECT OVERHEAD Cleaning, Clearing of Debris TOTAL AMOUNT OF PRELIMINARIES
QTY
UNIT
MATERIAL UNIT COST AMOUNT
-
-
-
-
-
-
LABOR UNIT COST AMOUNT
TOTAL AMOUNT
CIVIL & ARCHITECTURAL WORKS CEILING Supply and installation of gypsum perimeter ceiling Preparation and finishing of general paint on perimeter ceiling retouching of black paint on ceiling, new ducting, new wirings and tubings WALLS Supply and installation of double face dry wall gypsum board on metal framing Supply and installation of insolation wool for sound proofing Supply and laying of chb concrete wall plastering of concrete wall Preparation and finishing of wall in skimcoat industrial finish finishing painting of black paint on perimeter walls Supply and installation of 12mm thk glass partitions with frame FLOORING leveling and finishing of concrete cement flooring DOORS fabrication installation of 800mm x 2100 flush door with ducco paint finish supply and installation of 12mm thk. clear glass double door with complete set of fittings TOTAL AMOUNT OF ARCHITECTURAL WORKS TOTAL AMOUNT OF CONSTRUCTION
NOTE: 30% Downpayment 40% - 100% progress billing
0.00
0.00
-